Our Renovation Diary

We are currently adding all the previous updates by social media and email here so that we have a weekly history of the renovation. We are adding more photos and galleries over time. Simply click on the week to get the update; there is a link if there is a gallery of photos for that week.

Diary for 2020

  • End of week 2, brickwork complete

    3RD JULY

    The Jayflex team have been storming through the brickwork and are now ready to get the final steel in place for the roof. They have also inserted one above The Coach House doors as the lintel was found to be rotten. Huge progress and cudos to the guys.

    See more of the photos and detail in our renovation diary page for 3rd July.

    3RD JUNE

  • First full week of Coach House work

    26TH JUNE

    The Coach House has come on leaps and bounds. The steelwork has been inserted above the new concrete pads and the walls are being rebuilt.

    The Weekday Warriors have been back in and have painted the walls of The Stables. Next week they will be tackling a lot more in The Courtyard and with The Pub itself.

    See more of the photos and detail in our renovation diary page for 26th June.

    26TH JUNE

  • First full week of Coach House work

    19TH JUNE

    If you have strolled passed The Swan this week you will have seen that lots of work has been happening with The Coach House. Our local resident Brendan O’Reilly and his team from Jayflex have been in and achieved so much already.

    Have a wee peek and get more of the story on our renovation diary page for 19th June.

    19TH JUNE [RESTART]

  • Covid-19 Shutdown

    COVID-19 SHUTDOWN

    On this day, the UK Government decided to act decisively and put in measures for social distancing and a home lockdown. This was an unprecedented action that was required to protect the NHS and keep people safe. The Swan stopped all volunteering efforts in support.

    More and updated info can found on our Covid-19 page.

    23RD MARCH [SHUTDOWN]

  • Renovation update for 20th March

    20TH MARCH

    The volunteers have been doing some work this week. It has been a bit restricted in what can be done but we are taking baby steps in keeping the renovation going: adding signage within the bar area, paint stripping in various areas, and up on the roof to fix the temporary tarpaulin.

    It's been more of a week for moving furniture out to allow space for social distancing.

    Plans for having organised weekend volunteering days starting in the Spring have been unfortunately been postponed for now.

    Sorry, no photos for this week.

    20TH MARCH

  • Renovation update for 13th March

    13TH MARCH

    Another week when the weather hindered work outside. However inside, we got new shiny fire extinguishers and the Sewing Bee has been hard at it. Have a look!

    Gallery for the 13th March.

    13TH MARCH

  • Renovation update for 6th March

    6TH MARCH

    We took delivery of the new steels for the kitchen. Thes ewill be installed in the coming days when we have sufficient people about us.

    We hosted a team from O2 who had their team meeting in the School House. They also did some team building by re-painting the inside of the Coach House which will make it more presentable for the Spring and Summer.

    Gallery for the 6th March.

    6TH MARCH

  • In memoriam

    IN MEMORIAM

    Our very good friend and Weekday Warrior, Adrian Chojnacki, sadly passed away earlier this morning, Thursday 5th March. He will be greatly missed by us all. Our sincere condolences are offered to Dawn and the rest of their family.

    ADRIAN CHOJNACKI

  • Renovation update for 28th February

    UPDATE FOR THE 28TH FEBRUARY

    The guys continued digging for victory in the garden next door. They were joined by professionals who worked in the sealed transformer area.

    The guys also were working in the Stock Room putting together the new shelving. This was completed and stock returned back behind the locked door.

    Gallery for the 28th February.

    28TH FEBRUARY

  • Renovation update for 21st February

    UPDATE FOR THE 21st FEBRUARY

    The guys were digging for victory in the garden next door. The aim was to remove all the accumulated garden materials that was hard up against the kitchen wall of The Swan.

    And when it was wet, the guys were working inside making further improvements to the stock room. Hopefully this will be completed next week.

    Gallery for the 21st February.

    21ST FEBRUARY

  • Renovation update for 14th February

    UPDATE FOR THE 14th FEBRUARY

    Storm Ciara hit us and on the whole things were good. Only the tarpaulin on the Coach House was damaged and needed remedial work. Inside, the sparkies put up some lighting in the stock room and hall. In the stock room, the internal partition was taken down.

    Gallery for the 14th February.

    14TH FEBRUARY

  • Renovation update for 7th February

    UPDATE FOR THE 7th FEBRUARY

    Guys have been back on the roof this week. The weather was slightly better so that they could tackle the roofing issue under the blue tarpaulin; also the gable end too.

    And there was the addition of the bike racks to allow cyclists to securely stow there bikes under cover.

    Gallery for the 7th February.

    7TH FEBRUARY

  • Renovation update for 31st January

    UPDATE FOR THE 31ST JANUARY

    This week the guys have all but completed the fireboarding on the ground floor. Still some wee bits to do but it is a big step forward as we can now get the plastering done.

    And on the roof, the chimney was finally capped by a professional team donating their time.

    Gallery for the 31st January.

    31ST JANUARY

  • Renovation update for 24th January

    UPDATE FOR THE 24TH JANUARY

    Fireboarding continued in the hall and will continue into the room of doom and store room shortly. The kitchen was cleared in readiness to take the "stuff" from those rooms.

    Some wee things were done which have well received: putting up a coat hook in the ladies and also a couple of rows of them in the main bar. Makes it so much easier. Also the rugs have now been available.

    Out in the Coach House, there was further tidying and dump runs. The football table is now set up and ready for use.

    Painting continued in the office and there was some more wire stripping too.

    Gallery for the 24th January.

    24TH JANUARY

  • Renovation update for 17th January

    UPDATE FOR THE 17TH JANUARY

    Things you can see when you come down to the pub.... check out our new fireplace, complete with slate hearth that has been installed over the last week.

    Things you can't see as they are hidden away behind the scenes .... the flooring has been going down in pub's office and it is now ready for use.

    Gallery for the 17th January.

    17TH JANUARY

  • Renovation update for 10th January

    UPDATE FOR THE 10TH JANUARY

    The lads got stuck into the School Room to replace the removed chimney breast. A framework had to be built, and then covered with plasterboard. The original cladding was then re-instated. Yes it needs painted, but it is looking good.

    Elsewhere in the pub the office was painted and remedial work done to the toilets. Other remedial work is required over the coming weeks as the pub continues to live and grow.

    Gallery for the 10th January.

    10TH JANUARY

  • Renovation update for 3rd January

    UPDATE FOR THE 3RD JANUARY

    Guys were working in the School Room to remove the chimney breast. This required removal of a number of panels and then the careful disassembly. Work will continue at pace to make sure the room is ready for the start of the new school term.

    Coverings for the banquettes arrived from the Sewing Ladies. They look superb!

    Gallery for the 3rd January.

    3RD JANUARY


Diary for 2019

We received the keys on 2nd February 2019 and got stuck in fairly shortly afterwards. As well as special volunteering events, the Weekday Warriors along with Professionals have been renovating The Swan. First phase was the pub itself and the School House. These were almost completed in 2019.

Our diary for 2019 documents that. It is very similar to above with each week documented through our building update and also pictures taken by the team. Enjoy!