Renovation Diary: May 2022

6th May, 2022

A big thank you to McFarlane Telfer for coming out to us this week to fit the final parts to the kitchen equipment and make us fully operational. The last piece of the puzzle is the dishwasher extraction hood being fitted by Ron today. There’s been a big tidy and rearrange of the dry store in preparation of food orders and on Sunday there will be an intensive commercial clean to make the place glisten and shine. It is SO close! Watch this space…!

The Dry Store which is part of The Kitchen at The Swan.
Installation of the final extraction hood into The Kitchen at The Swan.
McFarlane Telfer hard at work in The Kitchen.

13th May, 2022

With the kitchen equipment professionally cleaned and in place, the focus turned to cleaning and tidying the surrounding areas in the calm before a busy Kitchen storm. While Micky, Josh and Ellie were placing food orders and trialling the equipment, the Warriors had a major tidy up. There were some final tweaks to electrics and fixtures and fittings and the back staircase is finished and looking beautiful. It has been a long hard graft to get to this point but we're very excited to see delicious dishes being prepared in the wonderful kitchen space.

Storing away tools in one of the stables.
Stacking up materials in bedroom 3.
Trevor and Lexie clearing out.

12th May, 2022

As you will have guessed, the renovation diary is written up every Friday night. By the Thursday 12th, The Kitchen was complete and ready for service. And that is exactly what happened, the first Epic Thursday by our School. And on Friday 14th, our new chef shows his talents with a Kitchen Test Day. See our May 2022 events diary for more details.