Renovation Diary: September 2021

Week 35/21: 3rd September 2021

An extraordinary team effort this week must be congratulated. The Weekday Warriors have been joined by GR6 staff and Micky, our General Manager. Collectively they have installed the ceiling boards in The Kitchen, begun the replacement of the wall and door into the dry-store room and even found time to take a pick axe to The Courtyard flooring. Always a busy week but some highly visible progress has been made this week. Sincere thanks to all those involved.

The lads working out what to do with the next board. Raising a board up to the ceiling ready for screwing
The new wall going up for The Store Room Richard Allen fitting a board
Thomas and Baffy Baff screwing in a board
Kitchen ceiling newly boarded Somewhere in there you can find Trevor

Some would say this is slo-mo but Micky has assured us that this was him at full speed ;)

Micky improving The Courtyard

Week 36/21: 10th September 2021

The Warriors have been hard at it again this week. The fire boarding of The Kitchen ceiling is now complete. Next week work will start on fitting the battens and boarding to the walls in readiness for plastering. To minimise disruption to GR6 pupils the Warriors also found time to install trunking for the power cables in The Stables.

Kitchen ceiling completely fireboarded
Trevor screwing in a ceiling board Team are looking tired
Another board being fitted in the ceiling Making sure the board butts up to the steel beam
Who needs a ladder when you have a large stack of fireboards Team cutting a fireoard to size

Meanwhile in the pub itself Micky was putting in a book case which will be stocked up in the very near future.

Sorting out the bookcase
Adding the pants for decoration
Adding the small chalk sign boards

Week 37/21: 17th September 2021

The Warriors have continued with the behind-the-scenes work in The Kitchen and The Storeroom Even thou' the school is now back, they are charging ahead getting ready for the 2nd fix of the electrics and the installation of the kitchen equipment.

Stairwell with final decorative boarding being put in place
Stairwell looking good

Following a report produced by a professional fire risk assessment company, the team could carry on with the plan: more fire boarding and preparing for battening the walls in The Kitchen. We will be adding some photos to the website shortly.

Putting in battons in the corridor ceiling
Preparing batons for The Kitchen
Ian clowning about with 1st fix wires on his head

For aficionados, this is the new staircase up to The School House with what was purported to be the tunnel to the church at its base. The staircase has had its 2nd fix cover this week, sounds simple but needs a lot of work and time.

Stairwell below ready for insulation and boarding
Insulaton is in
Boarding going on
Underneath the stairs now finished

Week 38/21: 24th September 2021

The Warriors have been prepapring The Kitchen walls for plasterboarding. As this have a lot of equipment attached to it, this has to be prepared very carefully with fixing points and supports all in the right place.

Warriors working in The Kitchen
Warriors working in The Kitchen

Aided by Ian the Plasterer, the Warriors have seen further significant progress this week. The Store Room ceiling has now been plastered and very shortly The Kitchen ceiling should have reached a similar milestone.

Ian the Plaster getting ready
Ian the Plasterer getting stuck in
Store room ceiling fireboarded ready for plastering
Finished Store Room ceiling

This week has seen the opening of the GR6 office, which you may have seen being installed in Stable One. This new space gives the GR6 team a breakout room for small sessions and meetings, as well as a therapeutic space. We're really pleased with the work that has been done and want to thank everyone in The Swan community for their patience whilst this vital work has been carried out.

Outside of stable 1
Inside stable 1

In parallel, Keith (Electrician) and the Warriors have been doing further work on the electrics for the stables - with the added advantage of improving the power supply to the outside heaters - winter is coming! Sorry, no photos of this.

Renovation Diary for July 2021 Renovation Diary for October 2021