Week 48/20: 27th November, 2020
A very busy time for the Weekday Warriors who have made great progress this week. Anyone walking past the gates recently should have seen that the tarmac has been removed revealing the concrete level.
With a mini digger onsite early this morning the Warriors will be able to dig a trench for the new electric cable to power the kitchen.
The Coach House now has its side door in place which will stop the drafts. There is still more old pointing to rake out and guttering to install.
Week 48/20: 29th November, 2020
We invited a few people who had intimated that they were happy to do some volunteering work during the present times. We were grateful that they came in and "tarted-up" The Bar. Giving it a refresh with a newlick of paint. We are so grateful that they came out and gave their time to spruce up the place ready for re-opening after Lockdown 2.0
Please note that appropriate Covid actions were taken on the day (e.g. social distancing) by the volunteers.