Renovation Diary: March 2022

4th March, 2022

Our volunteer Warriors remain very busy. The mammoth task of tiling is almost complete with just some final grouting to finish. Door frames have been installed in preparation for hanging the required, and very heavy, fire doors. The steel supporting the roof is now a tasteful anthracite in colour and the printer is ready to receive food orders placed at the bar - nearly there!

Lexie painting the steel support beam
The new integrated till for food ordering
Thomas building frame for The Kictchen door

And the Warriors continued with the tiling and grouting that is very, very time consuming. This not only makes the place aesthetically pleasing, but very easy to maintain in the future.

Tony and Ian hard at the tiling

11th March, 2022

The phrase watching paint dry is appropriate as much of the Warrior work this week has been about finishing the grouting of The Kitchen walls - not overly conducive to exciting photos! However, the photo does show a new ceiling being constructed to cover the many pipes and wires that have been installed in the corridor leading to The Kitchen. An important improvement that will provide a much needed enhancement to this access route.

Working in the corridor
Thomas hard at it

18th March, 2022

The Kitchen gets ever closer to the finish line. Sincere thanks to everyone involved with a special shout to 'young' Terry who braved the rain on Thu to sweep The Courtyard before continuing to tidy up inside. Thanks also to Simon from Windsor Joinery who delivered and installed the glass in the third and final Kitchen window.

Tony fixing electrics in The Cold Room John groutign in The Kitchn The Warriors working on the intenlall ceiling
Thomas fireboarding in the hallway John grouting in The Cold Room Ian puting battens in the steelwork in The Kitchen
Fitting pipework in The Cold Room Sealing aroung the new window in The Kitchen Tony preparing hole for an intake fan
Thomas measuring up fireboard ready for cutting Tidying up the floor Fitting the third and final window for The Kitchen

25th March, 2022

The work of the Warriors continues both inside and out. Tony has been hard at work in the corridor while John prepped and painted the new Kitchen windows. Plus Jenny adding a touch of spring to the courtyard.

Jenny adding a touch of spring to The Courtyard.
Tony cutting fireboard around the main electric panel
John painting one of the windows for The Kitchen
Another shot of John painting the new window fitted last week