We are back and running for 2022. The Warriors supported by professionals are working on the completion of The Kitchen. This page documents will document the renovations week-by-week during 2021.

  • 21st January 2022

    21ST JANUARY

    The moisture boarding is now complete and the walls ready for tiling, plastering or painting as appropriate. The guys have been working on the windows too getting ready for their installation whch has just started. The second electical fittings is also well underway.

    Our diary for week 3 of 2022 shows the transformation that is quickly occurring.

    21ST JANUARY

  • 14th January 2022

    14TH JANUARY

    The existing Kitchen equipment was given a final clean and then taken into The Kitchen ready for commissioning by McFarlane Telfer. Another electricity cable was pulled through and Keith was back beavering away. There are some picture of week 2 of 2022 of the transformation.

    14TH JANUARY

  • 7th January 2022

    7TH JANUARY

    A lot of progress in the back of the pub on The Kitchen, The Storeroom and The Coldroom. The guys were so busy that we didn't get that many photos of week 1 of 2022 renovations but what we have is there.

    7TH JANUARY