Renovations Diary: 19th March, 2021
As some of the kitchen equipment starts to arrive the Weekday Warriors have been hard at work preparing the site. Another skip was delivered early this morning as the tidying up continues. With new ceiling joists ready to be secured and a new staircase on order real progress is being made.


Meanwhile down below in The Stock Room there was some progress with the damp proofing on the external walls.


The clearout has started to tidy up The Courtyard for the re-opening hopefully on April 12th. Also we need to dump a lot of rubbsih from the renovation activities. The answer: a skip was required as we have so much bumf.


The team have also inserted SFJC Safety Fast Joist Caps into the backwall that will then be used to further support The School Floor at the point The Kitchen extraction transits through. In the nicer weather, the lads were treating the rafters before insertion.



And McFarlane Telfer delivered a number of The Kitchen appliances with have been securely stored away. Did we mention the pizza over? This is going to add a lot to our food offering when The Kitchen is opened fully.

And it was one young's birthday too - so the lad celebrated with a couple of well deserved beers at the end of the day.


With Easter nearly upon us there is a real feeling of 'spring is in the air' as every working day brings us closer to being able to provide our own food service.