Renovations Diary: 20th September, 2019
Project Manager's Report
We have had a Productive week at The Swan.
The men's urinals are now up and running and we have started decoration to the men's loos.
We have sourced some really lovely Moroccan style mirrors for ladies room and it has given the room the wow factor . We still have decoration touch ups to do.
Next week we will be fitting the baby change units to both the men’s and ladies toilets.
The skirtings have been cut to size and are ready to fit.
We now have WiFi and a television in situ which is a real milestone.
The electrical works are almost complete and the external wall lanterns that have been lovingly restored by Baz and Diane will be fitted today.
We have been working on the main windows that we will start painting next week.
The school room opened its doors this week and looks fantastic and we have already had some interest from people looking to rent the space.
Pete our resident builder will be back next week and is going to complete the bar and start creating some fabulous window seating.
We have radiators ! All have been fitted now and will be connected and working next week.
The Swan opened its doors on Monday morning and nobody seemed to mind being amongst our regular volunteers armed with hammers, drills and paint brushes . We now serve delicious cakes and coffee from 9.30 am.
Have a super weekend.
Marilyn x
Coffee and cakes from 9:30am

Flush test in gents

School room ready for action

Where to put the mirror?

Lindsay Court guessed weight of the copper

School room breifing

New mirror in the ladies

Marilyn removing another test

School room briefing

Ladies outer room