Renovations Diary: 19th July, 2019
Considerable work was done this week in the ladies loo to get it ready for the opening. It was one of the "must have's to allow us to open. Pete and Tony took the lead supported by Scott the Plumber and the volunteers.
Plumbing installed

Heating installed

New wall plastered (RHS) and floor laid

Marilyn got involved in the painting

Door frames readied

Pete the Builder laying the tiles

Preparing the vanity unit

Door removed readied for final bricking

Tony cutting the fiddly bits

Toilet ready for Saturday's opening

Whilst the building team focussed on the ladies toilet, the volunteers were working on the plasterboarding and to allow the plastering team to do their stuff. There was a lot to do and there was some long evenings to try and get the ceiling and pillars done. Still a lot to do after the opening but a huge step forward.
Pink plasterboard is fire retardant

First fixing by sparkies completed

The plastering team

Richard from #3 taping up

Complex board sorted out by the team

The pub was sectioned into workable areas

Steels being wrapped up

Getting there with the boarding

First skim done

Drying ceiling plaster

Stuart, owner of the plastering company

New boards often needed support

Every board was individual cut

Ian our volunteer plasterer

Looking good

John and Graham got stuck into the alcove door which Richard D had opened up. This allowed the removal of a door that was essentially never used and took up a lot of space. This will be receiving insulated fireboard before being plastered and finished with a benchseat.
John bricking up the alcove door

Graham was the other half of the team

Almost finished

Other work was done to make the pub and courtyard attractive.
Hiding the building materials

Miranda painting the signs

Team planting up the flowers

John painting "Riverbank Green"
