Progress with the Renovation - Update for the 3rd May

What's being happening in the last week:

  • Footings completed for the concrete padstones required for the new stel supports.
  • Started plastering gents toilet.
  • Prep work for new boiler and water tanks carried out.
  • GRS were clearing rubble and prepping their school room.
  • Further scaffolding was put in place.
  • First round of paint matching tests against The Swan colours completed.